A change order is a signed, written agreement that changes the work, the price or the schedule after your renovation contract is already in place. If you want something different, or the crew finds something behind a wall, the change goes on paper with a price and a schedule effect before anyone picks up a tool. That is how you keep a job on budget. After 25 years of sealing and repairing buildings around Oshawa, we have seen that most disputes start with a verbal “sure, go ahead” that nobody wrote down.
TL;DR
- A change order is a mini-contract: it describes the altered work, the cost and the schedule effect, and both you and the contractor sign it.
- In Ontario, if your contract includes an estimate, the contractor generally cannot charge more than 10% above it unless you required extra or different work and signed a change to the contract.
- Ask for the price of a change first, then give permission to proceed as a separate step.
- Track the running total of approved changes. Small ones add up.
- A change order alters the contract. An addendum or appendix attached to the contract carries the same legal weight, and changing it is also a change to the contract.
Table of Contents
- What a change order is and when you need one
- What usually triggers a change order
- Change order vs addendum
- What the Ontario rules say
- What a good change order includes
- How to handle a change, step by step
- For property managers, landlords and contractors
- Our perspective
- If your project includes caulking or sealing
- FAQ
- Sources
What a change order is and when you need one
The Canadian Home Builders’ Association describes a change order as a mini-contract that defines altered or additional work, including payment terms. You need one whenever the plan you signed changes: extending new flooring into the next room, swapping a fixture, or dealing with a hidden problem such as rotted wood or unsafe wiring. It only becomes part of the contract once both parties sign.
The starting point is always the original scope. A vague original scope makes it harder to tell a legitimate change from work already included. That is why the first question on any extra is: was this already in the drawings, the specifications or an allowance? If yes, it is not an extra. A change should not be called an extra just because it was missing from the contractor’s estimate when the contract already required it.
What usually triggers a change order
Ontario contractors group the causes into four types: owner requests, concealed conditions, design or authority revisions, and product or schedule changes.
- Owner requests. You pick a different tile, add a window, move an outlet. The most common and the easiest to control.
- Concealed conditions. Rot, old wiring, damaged sheathing. Hidden deficiencies are typically excluded from the agreed price and need your approval before the extra work starts.
- Design or authority changes. An inspector or the municipality asks for something different.
- Product or schedule changes. A product is discontinued or late, and a substitute is needed.
On exterior work in the Durham Region, concealed conditions are the usual one. Once old caulking and trim come off, you sometimes find water-damaged framing or a failed brick sill that nobody could see from the ground. That is normal, and it is exactly why the paperwork exists.
Contingency and allowances are not change orders
Many contracts set aside a contingency for things that cannot be known until work is underway, such as the condition of roof sheathing. It should be tied to a specific part of the project and approved by you before it is used. An allowance is different: it sets an amount for an item not yet chosen when the contract was written, whereas a change order modifies work already established. If you are weighing how a fixed budget line differs from an agreed change, this explanation of how an allowance works is a helpful comparison.
Change order vs addendum
People use the terms loosely, and the difference is mostly about timing and purpose.
| Change order | Addendum or appendix | |
|---|---|---|
| When | After the contract is signed, as work progresses | Often attached to the contract at signing, or added to it |
| Purpose | Alters scope, price or schedule | Adds detail or terms, such as schedules or specifications |
| Legal weight | Becomes part of the contract once both sign | Same legal weight as the main form |
The practical point: a change to an appendix is a change to the contract and has to be handled as one. Whatever your paper is called, if it changes what you pay or what gets built, get both signatures.
What the Ontario rules say
Ontario’s government guidance says that any proposed change in the scope of work must be documented and communicated in writing, with both parties signing the changed contract, so both sides understand the effect on price, scheduling and completion dates.

The same guidance covers the 10% rule. If the contract includes an estimate, a contractor cannot charge more than 10% above it unless you required additional or different goods or services and a signed change to the contract exists. It is not permission to add an unexplained 9.9%: the parties can amend the price when you require extra or different work, and that is done through a change order.
As of reports in 2026, Ontario’s replacement Consumer Protection Act, 2023 had not yet been proclaimed in force, so the 2002 Act still applies to renovations. Check the Ontario government site for the current status. If a dispute is serious, speak to a lawyer or contact Consumer Protection Ontario.
Can you approve a change order electronically?
Often, yes. Ontario’s Electronic Commerce Act, 2000 generally recognizes electronic documents and signatures, subject to the approval method your contract specifies. Use the method written into your contract, and keep the signed copy. If your project also needs revised permit drawings, a permit drawing service for Ontario projects can prepare them.
What a good change order includes
A clear change order should name the project, the parties, the original contract, the change number and the date. Then it should cover:
- The reason for the change.
- Work added and work removed, with credits for deletions.
- Materials, labour, subcontractors, equipment, delivery, disposal and permits.
- Markup, tax and the net total.
- The revised contract total and the schedule effect, including “no effect” when that is true.
How extras are priced should be in your contract from day one. The CHBA’s guide for renovators lists material cost plus hourly rate, labour and material plus a percentage, or an agreed lump sum, with deletions calculated at cost less 10%. Cutting work back can also carry a cost: a contractor may charge a percentage of the value of cancelled work.
A worked example
Say you have a contract to reseal and trim the windows on a two-storey home. Midway through, the crew uncovers a rotted sill. The change order might read: Change No. 1, reason: concealed rot at north-facing sill; added work: remove and replace sill, new sealant; credit: none; net total with tax; schedule effect: one added working day. You review it, sign it, and only then does the extra work start. The revised contract total is written at the bottom, so you always know where you stand.
How to handle a change, step by step
- Describe the change. Say what you want, or what was found.
- Check it against the original scope. Identify the drawing, specification, allowance or exclusion it touches.
- Ask for a price and a schedule effect. Keep a request for pricing separate from permission to proceed.
- Decide before the work is done. Timing drives cost: a change before materials are ordered is relatively simple, while the same change afterwards can mean cancellation, removal and re-ordering.
- Sign. Both parties, by the method your contract names.
- Update your running total. Individually manageable changes can add up to a substantial increase.
Zero-dollar changes still need paper
Even a swap at the same price can shift the schedule. In one Ontario example, a replacement vanity cost the same but had a different drawer layout, which meant revising the rough-in plumbing. A renovator should also document zero-cost changes in writing, since processing them takes staff time, and you are responsible for timely decisions so the job does not stall.

Urgent work
If something has to be done right away to protect people, property or finished work, such as an active leak, the work can proceed, but the circumstances and the work performed should be documented as soon as reasonably practical.
Why texts and emails are not enough
Scattered messages are hard to rely on later. A “go ahead” text is difficult to interpret if several versions or prices were discussed. The Ontario courts have also shown that the paper trail matters both ways: in one 2017 case the court found that oral approval of separate work could waive a contract’s written-change-order requirement. Do not count on that working in your favour. Write it down.
For property managers, landlords and contractors
If you manage a multi-unit building or a commercial property, the same discipline applies at a larger scale. Keep one change log per project, number every change and link each to the contract documents. Quick authorization keeps crews working: roofing industry guidelines say change-order requests and written authorization should be expedited, and schedules updated as changes occur.
If you are a general contractor, put the caulking and sealing scope in your bid in detail so envelope work does not turn into a surprise extra. We cover that in how to include caulking in your renovation bid, and why sealing sits on the schedule in why caulking is on the critical path.
Our perspective
Most change orders we see on exterior jobs come from the same place: a scope that was vague about the joints. Is the old sealant being removed or just topped up? Are the sills and brick part of the price, or an exclusion? When that is written down at the start, the surprises that remain are real concealed conditions, and those are easy to explain.
We would rather you read a clear change order twice than approve a verbal one in a hurry. Ontario’s freeze-thaw cycles punish quick fixes, so a change that gets priced properly now beats a patch that fails by spring. Our approach is clear communication and honest pricing, and a change order is just that applied to a mid-job decision.
Felix
If your project includes caulking or sealing
We handle caulking and sealing for homes and commercial properties across the Greater Toronto Area, including window caulking, door sealing and building envelope sealing. We also do window and door installation and brick and masonry repairs, so related work can sit under one scope.

Tell us what your building needs and we will put the scope in writing. Start at kettlecontracting.com.
FAQ
Can a contractor charge more than the estimate in Ontario?
Generally not by more than 10%, if the estimate is in your contract. The exception is when you require additional or different work and there is a signed change to the contract. Anything beyond that should be explained in writing.
Do I have to sign a change order for a small change?
Yes, in practice. Even small or zero-cost changes should be documented, because they can still affect time and cost. A short written record signed by both sides is enough.
What if I do not approve the change?
Then the contractor must stay with the original contract and design. Where a change is a hidden deficiency, your approval is needed before the extra work begins, which protects both sides.
Is a change order the same as an addendum?
Not exactly. A change order alters the work, price or schedule once the job is underway. An addendum or appendix is part of the contract with the same legal weight, so changing one is also a contract change.
Sources
- The Renovation Process, Canadian Home Builders’ Association
- Construction Change Orders Ontario, Owner’s Guide
- Construction Change Orders Ontario: Control Extras
- Ontario Renovation Change Orders Explained
- Residential Renovation Contracts, CHBA 2018
- Homeowner guide to renovation contracts, CHBA
- A guide for home renovation and roofing businesses, Ontario.ca
- How to Hire a Contractor in the GTA
- Conterra Restoration Ltd. v. Kirsch, 2017 ONSC 3152
- How to manage changes to your home renovation
- Roofing project submittal and protocol guidelines, 2023